The project will upgrade the Agassiz-Rosedale Bridge to improve safety, reliability and extend its service life. It is located on the Fraser River between Agassiz and Rosedale/Bridal Falls.
Notification of project-related fieldwork or construction is posted on this page in advance. For the latest information on road conditions, please visit DriveBC.
To receive a notification when this page is updated, please subscribe using the form at the bottom of this page.
Most of the work will take place underneath the bridge. However, some work on the bridge deck will require single-lane, alternating traffic.
To minimize impacts on drivers, these closures will generally be scheduled during months when traffic volumes are lower. The length of closures will also be managed based on traffic conditions.
Expect nightly lane closures so the contractor can safely advance work.
| Open | Open, no scheduled delays |
|---|---|
| SLAT |
Maximum delay: 15 minutes |
| Closed | No through traffic |
| Sun | Mon | Tues | Wed | Thur | Fri | Sat | |
|---|---|---|---|---|---|---|---|
| 5 am to 11 pm | Open | Open | Open | Open | Open | Open | Open |
| 11 pm to 5 am | SLAT | SLAT | SLAT | SLAT | SLAT | SLAT | SLAT |
| Sun | Mon | Tues | Wed | Thur | Fri | Sat | |
|---|---|---|---|---|---|---|---|
| 24 hours | SLAT | SLAT | SLAT | SLAT | SLAT | SLAT | SLAT |
The Agassiz-Rosedale Bridge carries nearly 15,000 vehicles each day across the Fraser River between Agassiz and Rosedale/Bridal Falls. The bridge, which opened in 1956, carries two lanes of Highway 9 between Highway 1 and Highway 7 and serves local communities on both sides of the Fraser River.
The project will address deterioration of the bridge’s structural steel and concrete, improve drainage and extend the operational service life of the bridge by an estimated 50 years.
Key work will include:
The bridge is an important connection for people, goods and communities in the Fraser Valley. These upgrades will help maintain this vital connection and support safer, more reliable travel for decades to come.
The contract was awarded to B.C.-based company Graham Infrastructure LP.
$64 million
The Agassiz-Rosedale Bridge is 1,870 m long. During construction the construction zones on the bridge will be 150 m long or 300 m long with single-lane alternating traffic.
| Month | Status |
|---|---|
| January | Full-time (24/7) SLAT (300 m work zone) |
| February | Full-time (24/7) SLAT (300 m work zone) |
| March | Full-time (24/7) SLAT (150 m work zone) |
| April | Overnight SLAT (300 m work zone) Monday to Friday from 7 pm to 6 am Saturday and Sunday from 7 pm to 8 am |
| May | Overnight SLAT (300 m work zone) Monday to Friday from 7 pm to 6 am Saturday and Sunday from 7 pm to 8 am |
| June | Overnight SLAT (300 m work zone) Monday to Friday from 7 pm to 6 am Saturday and Sunday from 7 pm to 8 am |
| July | Overnight SLAT (300 m work zone) Monday to Friday from 7 pm to 6 am Saturday and Sunday from 7 pm to 8 am |
| August | Overnight SLAT (300 m work zone) Monday to Friday from 7 pm to 6 am Saturday and Sunday from 7 pm to 8 am |
| September | Overnight SLAT (300 m work zone) Monday to Friday from 7 pm to 6 am Saturday and Sunday from 7 pm to 8 am |
| October | Full-time (24/7) SLAT (150 m work zone) |
| November | Full-time (24/7) SLAT (150 m work zone) |
| December | Full-time (24/7) SLAT (300 m work zone) |