Phase 2: Cache Creek Channel Reconstruction Project

Last updated on June 30, 2026

an aerial photo of a completed bridge over cache creek

Aerial photo of the cetéqmén Bridge in Fall of 2024.

After multiple floods of Cache Creek in recent years, the installation of the cetéqmén Bridge was completed in the Fall of 2024. This 13-metre-long, four-lane bridge replaced the culvert that ran under the previous Highway 97 crossing. It is designed to accommodate increased water flows due to climate change and ensure resilience against future flooding, particularly peak flows during spring freshet. 

Notice of Work

One building located in the Cache Creek Channel Reconstruction Project area is scheduled to be taken down and removed this summer. The removal of this building, which is located at Highway 97 and Collins Road, will provide space required for upcoming channel reconstruction work.

Please obey signage and personnel when this work is underway.

Phase 2

Rendering of Phase 2 Reconstruction work showing extents from Approximately 1260 Stage Road to Bonapart River

Aerial illustration of the extents of Phase 2 creek reconstruction works from approximately 1260 Stage Road to the Bonaparte River, through the Village of Cache Creek

Ongoing work to restore capacity of the creek remains a top priority for the Ministry of Transportation and Transit and the Village of Cache Creek. A second phase of the project is anticipated to begin in late 2026, with creek reconstruction work taking place from Stage Road to the Bonaparte River. The Ministry will also deliver construction of a new Quartz Road bridge on behalf of the Village.

Project benefits

Resiliency work establishing the channel downstream and upstream of the cetéqmén Bridge will have a number of benefits, including:

  • Enhanced capacity of the channel
  • Improved water flow by removing constraints in the channel 
  • Better resilience to extreme weather events, by placing rock along the bank, or “armouring” the channel
  • Restoration of environmental features to support the overall project footprint

Rendering of Phase 2 work in the channel.
Rendering of Phase 2 creek reconstruction work from the Bonaparte River looking east

Status

Detailed design and environmental permits are being finalized.

Early work, including demolition of one building, is expected to take place in Summer 2026.

Channel reconstruction work and construction of the Village’s crossing at Quartz Road is planned through 2027.

During construction people travelling through the area may notice minor traffic interruptions on Highways 1 and 97 as well as on local roads.

Archive

 

Progress updates

Fall 2024

Installation of the cetéqmén Bridge to accommodate increased water flows and ensure resilience against future flooding was completed Fall 2024. The name cetéqmén means water crossing.

February 2024

February 2024 overview of completed, ongoing and upcoming construction activities (PDF, 761KB).

October 2023

A public information session was held in Cache Creek on October 4, 2023.

You can share your feedback with the project manager. Use the subscribe feature to be informed of updates to this page. 

 

Notifications

June 2025

As part of technical information-gathering, geotechnical investigations are set to take place the week of June 30th, 2025. 

September 2024

Bridge and road construction is ongoing, with crews currently working on the west side of the bridge. One lane in each direction will be maintained through the project area, though drivers can expect intermittent single-lane alternating traffic with delays of up to 5 minutes until mid-October. A construction speed zone of 30 km/hour is in effect.

July 2024

Crews are currently on site working on the east side of the bridge structure. Bridge and road construction is ongoing. Crews are currently working on the east side of the new crossing. One lane in each direction will be maintained through the project area. In July, drivers may experience single-lane alternating traffic with stoppages of up to five minutes. Please watch for construction and traffic personnel while in the area and visit DriveBC for further information.

April 2024

Starting on April 12, crews will be on site working on the northbound lanes. Bridge foundation and channel realignment work continues. Businesses in the project area will remain open during this time. Please watch for construction and traffic personnel while in the area and visit DriveBC for further information.

March 2024

Work to date has included excavation and the installation of a temporary lock block wall. Bridge foundations and channel realignment work continues. Please watch for construction and traffic personnel while in the area and visit DriveBC for further information.
The project is scheduled to be complete later this summer.

February 2024
The construction contract for the Cache Creek Restoration Project was awarded to Acres Enterprises Ltd., who has partnered with Bonaparte First Nation, and construction began in January. Work in the coming weeks includes excavation and the installation of a temporary lock block wall, bridge foundations, and channel realignment work. Please watch for construction and traffic personnel while in the area and visit DriveBC for further information.
The project is scheduled to be complete later this summer.

December 2023
Over the coming months, construction crews are completing preparation work in advance of bridge construction, which includes diverting water in the creek, temporarily removing a portion of culvert and completing a watermain relocation. Please watch for construction and traffic personnel.

October 2023
Starting late October, Ministry contractors will be on-site surveying the project area in advance of watermain work.

 

Photo gallery

 

Contact information

Friendly Url for this Page:
gov.bc.ca/cachecreek

For information about this project, contact:

Alvin Brulotte
Project Manager

Media Inquiries Phone
250-356-8421