Project No. 14095-0001

Last updated on August 14, 2023

Chilliwack Lake Road - Chilliwack River Valley Flood Repairs


Submission for Tenders Expires: August 23, 2023

Project Number: 14095-0001

Contract ID: 14095MJ0001

Location: Site B is located on the Chilliwack Lake Road, approximately 5.0km east of the Vedder Road Roundabout; Site C is located on Edwards Road, 5.2km east of the Vedder Road Roundabout; Site D is located on Chilliwack Lake Road, approximately 4.2km east of the Chilliwack River Bridge.

Description: Coordination of utilities, survey layout, erosion and sediment control, clearing and grubbing, organic stripping, roadway and drainage excavation, supply and placement of drainage appliances, geosynthetic installations, supply and placement of granular materials, supply and placement of riprap, supply and installation of concrete lock block wall, pavement cutting and removal, removal and relocation of signs and concrete barrier, supply and place hot mix asphalt, and revegetation seeding.

 

Document
Number

Document Description

1

Chilliwack Lake Road – Site D Box Culvert at Anderson Creek (2023) - Stantec

2

Chilliwack BC Flood Recovery Project – Site C Conceptual Design of Retaining Wall (2023) – WSP Canada

3

Cross Sections

4

Chilliwack Lake Road- Chilliwack River Valley Flood Recovery: Tender Data - Stantec, 2023