Project No. 13254-0001

Last updated on April 30, 2024

Highway 1 – Peardonville Road to McCallum Road Median Soil Removal


Submission for Tenders Expires: May 7, 2024

Project Number: 13254-0001

Contract ID: 13254MJ0001

Location: Median of Highway 1 starting immediately west of Peardonville Road Underpass and ending approximately 1.5 km west of the McCallum Road Underpass.  Eastbound LKI Segment 0520 km 11.02 to km 14.47, and Westbound LKI Segment 0521 km 6.97 to km 3.53.

Description: Work includes but is not limited to the following: Traffic Management, Quality Management, Protection of the Environment, Survey and layout, Grubbing, Organic Stripping, stockpiling and respreading, Type D excavation, Supply and placement of roadside barrier, Construction of access roads, Embankment and shoulder widening for barrier flare construction, Supply and install asphalt for barrier flare and roadside barriers, Median grading and Revegetation seeding.

 

Document
Number

Document Description

1

Cross Sections 

2


Borehole Test Pit Logs

3

Step B Soil Characterization Program, Phase 3B Advanced Works Median Soil Removal, Peardonville Road to McCallum Road, Fraser Valley Highway 1 Corridor Improvement Program, Abbotsford, BC

4

01615 Peardonville Road Underpass Record Drawings

5

2300 Civil 3D Tender Data 

6

Fraser Valley Highway 1 Corridor Improvement Program, Project Labour Agreement

7

Letter for FVH1CIP Additional Scope of Work

8

Fraser Valley Highway 1 Corridor Improvement Program Project Labour Agreement -Wage Grids May 2024