Quesnel-Hixon Road

Last updated on April 29, 2026

An aerial view of Quesnel-Hixon Road and the Cottonwood River Canyon Bridge. April 30, 2024

Closed. Safety improvements to nearby roads and the rehabilitation of the Ahbau Creek Bridge will be undertaken following a landslide.

Status

Residents who live along Quesnel-Hixon Road will soon have improved access via the Highway 97-Olson Road intersection. Construction is scheduled to start this summer, when crews will begin widening the highway in the area, adding northbound and southbound left-turn lanes, and extending the paved shoulder for right-turning vehicles. Olson Road will also be resurfaced from Highway 97 to Quesnel-Hixon Road, as well as sightline and drainage improvements in certain sections.

Further south, the Ahbau Creek Bridge will be rehabilitated and strengthened to improve safety, extend its service life and increase the posted load limit for the crossing. Vehicle turnarounds will also be constructed on either side of the Cottonwood River Canyon Bridge, which will be permanently closed, and a rest area will be built near the former north bridge approach.

 

Quesnel-Hixon Road Map shows areas of work.

Olson Road is located 29 km north of Quesnel along Highway 97. The Ahbau Creek Bridge is a further 8 km west, accessed via Olson Road and Quesnel-Hixon Road. 


Traffic impacts

Notification of project-related fieldwork or construction is posted on this page in advance. For the latest information on road conditions, please visit DriveBC.

Timeline

Construction is expected to take place in 2026. Updates will be posted here as planning progresses and schedules are confirmed.

Public engagement

If you have feedback or questions, please get in touch with the project manager.

Archive​

 

Progress updates

October 2025
Based on technical assessments and local feedback from the Quesnel-Hixon Road Community Liaison Group, the Ministry is proceeding with improvements on the Quesnel-Hixon Road Project to improve safety, capacity and long-term reliability. These upgrades include intersection improvements at Olson Road and Highway 97, highway widening and the addition of a northbound left-turn lane. Roadside brushing along sections of Olson Road and rehabilitation of the Ahbau Creek Bridge will also occur.

August 2024
After three years of planning and extensive options analysis, a decision was made to permanently close a 400-metre section of the road and take the Cottonwood River Canyon Bridge out of service. This decision was made to ensure public safety and manage taxpayer funds wisely. Alternate routes, such as Olson Road, continue to provide access to Highway 97 for residents north of the slide, and accommodate current traffic volumes.
The Ministry is evaluating potential safety improvements to existing roads in the area.  

July 2024
Environmental fieldwork and geotechnical investigations at the Cottonwood River Canyon Bridge were completed, with crews collecting data and samples for project planning.

June 2024
Geotechnical investigations were completed near both ends of Ahbau Creek Bridge as part of the exploratory process, allowing for further reconnaissance as long-term solutions are developed.

January 2024
A survey crew mapped the area to inform project planning.

August 2023
Crews conducted visual inspections along Quesnel-Hixon Road, as well as hammer sounding on the Cottonwood River Canyon Bridge and the Cinema-Old/Ahbau Creek Bridge to inform project planning.

June 2022
Geotechnical investigations were completed as part of the exploratory process, allowing for further reconnaissance as long-term solutions are developed.

March 2022
A program-wide engagement period was held to introduce the public to the projects, providing context and an overview of the background, process, and short-listed options being explored.

November 2021
An in-person drop-in session was held at Kersley Hall to provide updates on the Quesnel-Hixon Project.

April 2021
A landslide during the 2021 freshet caused a complete loss of the Quesnel-Hixon Road. Quesnel-Hixon Road and Cottonwood Bridge have been closed while long-term solutions are being explored. Vehicle turnarounds were set up before the closure points, and traffic is being diverted to Highway 97 on Olson Road.

 

Notifications

August 2024
Geotechnical investigations at the Cottonwood River Canyon Bridge are now complete. Crews and equipment will remain in the area for approximately one week for site restoration. 

July 2024
Geotechnical investigations are underway around Cottonwood River Canyon Bridge. No traffic impacts are expected, but we ask residents to stay clear from work areas for their safety.

July 2024
Environmental fieldwork is also underway and is expected to continue until the end of July in the Quesnel-Hixon Road Project area, with crews collecting data and samples for project planning.

June 2024
Starting June 10, for approximately one week, Quesnel-Hixon Road near both ends of Ahbau Creek Bridge will be reduced to one lane alternating in each direction. This setup will be in place from 7 a.m. to 5 p.m each day to conduct geotechnical investigations. More information on this work is available here.

August 2023
On August 14-18, 2023, crews conducted visual environmental inspections along Quesnel-Hixon Road, Cottonwood River Canyon Bridge and Cinema-Old/Ahbau Creek Bridge crossing locations, and Naver Creek. Both assessments will inform long-term planning for both bridges and Quesnel-Hixon Road. 

 

Photo gallery

Contact information

For more information contact:

Tom Kearns
Project Manager

Media Inquiries Phone
250-356-8241