
Closed. Construction is underway on improvements to the safety and long-term reliability of the local road network following a landslide.
Construction is underway on improvements to the safety and long-term reliability of the local road network following the 2021 landslide and closure of Quesnel-Hixon Road.
The work is being delivered through two separate construction scopes.
Olson Road safety improvements include:
Further south, bridge and permanent road closure work includes:

Olson Road is located 29 km north of Quesnel along Highway 97. The Cinema-Old/Ahbau Creek Bridge is a further 8 km west, accessed via Olson Road and Quesnel-Hixon Road.
During the Olson Road safety improvements, residents and road users may experience:
During the bridge and permanent road closure work:
Advance notice of bridge closures and other major traffic impacts will be posted on this page and DriveBC.ca. Signage will be posted before closures or major disruptions, where possible, and traffic control personnel will direct traffic when required.
Construction is underway, with major work expected to be completed in 2026 and minor work continuing into spring and summer 2027.
If you have feedback or questions, please get in touch with the project manager.
Enviro-Ex Contracting Ltd. has been awarded the contract to deliver the Olson Road safety improvements. Construction is underway.
Blackbird Industrial Ltd. has been awarded the contract to deliver the separate Cinema-Old/Ahbau Creek Bridge rehabilitation, Cottonwood River Canyon Bridge removal and permanent road closure work. Construction on this scope is expected to begin in mid-August 2026.
Based on technical assessments and local feedback from the Quesnel-Hixon Road Community Liaison Group, the Ministry is proceeding with improvements on the Quesnel-Hixon Road Project to improve safety, capacity and long-term reliability. These upgrades include intersection improvements at Olson Road and Highway 97, highway widening and the addition of a northbound left-turn lane. Roadside brushing along sections of Olson Road and rehabilitation of the Cinema-Old/Ahbau Creek Bridge will also occur.
After three years of planning and extensive options analysis, a decision was made to permanently close a 400-metre section of the road and take the Cottonwood River Canyon Bridge out of service. This decision was made to ensure public safety and manage taxpayer funds wisely. Alternate routes, such as Olson Road, continue to provide access to Highway 97 for residents north of the slide, and accommodate current traffic volumes.
The Ministry is evaluating potential safety improvements to existing roads in the area.
Environmental fieldwork and geotechnical investigations at the Cottonwood River Canyon Bridge were completed, with crews collecting data and samples for project planning.
Geotechnical investigations were completed near both ends of Cinema-Old/Ahbau Creek Bridge as part of the exploratory process, allowing for further reconnaissance as long-term solutions are developed.
A survey crew mapped the area to inform project planning.
Crews conducted visual inspections along Quesnel-Hixon Road, as well as hammer sounding on the Cottonwood River Canyon Bridge and the Cinema-Old/Ahbau Creek Bridge to inform project planning.
Geotechnical investigations were completed as part of the exploratory process, allowing for further reconnaissance as long-term solutions are developed.
A program-wide engagement period was held to introduce the public to the projects, providing context and an overview of the background, process, and short-listed options being explored.
An in-person drop-in session was held at Kersley Hall to provide updates on the Quesnel-Hixon Project.
A landslide during the 2021 freshet caused a complete loss of the Quesnel-Hixon Road. Quesnel-Hixon Road and Cottonwood Bridge have been closed while long-term solutions are being explored. Vehicle turnarounds were set up before the closure points, and traffic is being diverted to Highway 97 on Olson Road.
Geotechnical investigations at the Cottonwood River Canyon Bridge are now complete. Crews and equipment will remain in the area for approximately one week for site restoration.
Geotechnical investigations are underway around Cottonwood River Canyon Bridge. No traffic impacts are expected, but we ask residents to stay clear from work areas for their safety.
Environmental fieldwork is also underway and is expected to continue until the end of July in the Quesnel-Hixon Road Project area, with crews collecting data and samples for project planning.
Starting June 10, for approximately one week, Quesnel-Hixon Road near both ends of Cinema-Old/Ahbau Creek Bridge will be reduced to one lane alternating in each direction. This setup will be in place from 7:00 am to 5:00 pm each day to conduct geotechnical investigations. For more information, see Quesnel-Hixon Road Project (PDF, 4.3MB).
On August 14 to 18, 2023, crews conducted visual environmental inspections along Quesnel-Hixon Road, Cottonwood River Canyon Bridge and Cinema-Old/Ahbau Creek Bridge crossing locations, and Naver Creek. Both assessments will inform long-term planning for both bridges and Quesnel-Hixon Road.
Enter your email address to subscribe to updates of this page.