Highway 97 at Cuisson Creek

Last updated on April 5, 2024

Aerial photo of slide damage along Highway 97 at Cuisson Creek – May 2021

Open. Multiple landslides in 2021 created a risk of erosion, which could affect the use of Highway 97 if left unaddressed.

Location map

Highway 97 at Cuisson Creek Map Presents 4 options for moving the road for discussion, location of the railway and the area of the landslide

Highway 97 at Cuisson Creek is located approximately 46 km south of Quesnel.


Status

After a comprehensive and technically driven process that began in late 2020, we are proceeding with a plan to make shoulder protection and drainage improvements on Highway 97 at Cuisson Creek.

This decision follows the completion of extensive planning, detailed design work, and geotechnical investigation over the past three years that confirmed these works will help ensure safety for road users.

Traffic impacts

The road remains open. Residents can expect crews and equipment onsite as preconstruction begins. For the latest information on road conditions, please visit DriveBC.

Timeline

Preconstruction activities may be seen on Highway 97 at Cuisson Creek as early as spring 2024. Once construction begins, it is expected to take approximately two months to complete. 

Project and construction updates are anticipated as plans and scheduled are confirmed.

Public engagement

You can share your feedback with the project manager. Use the subscribe feature to be informed of opportunities for public engagement and updates to this page. 

Archive

 

Progress Updates

February 2023
A geotechnical drilling program was carried out in the Highway 97 at Cuisson Creek Project area. Crews used a drill rig to create a test hole in the ground to collect soil and water samples.

March 2022
A program-wide engagement period was held to introduce the public to the projects, providing context and an overview of the background, process, and short-listed options being explored.

November 2021
An in-person drop-in session at Kersley Hall was held to provide updates on the Highway 97 at Cuisson Creek Project.

July 2021
Construction activities were completed, including fixing the cracked pavement and other surface damage to improve driving conditions.

April 2020
During the spring freshet, multiple historic landslides were reactivated along Highway 97 at Cuisson Creek. The crest of the erosion is approximately 10 metres from the highway shoulder.

 

Notifications

October 2023
As part of ongoing project planning, field surveys took place on Church Road and Highway 97.

 

Photo Gallery ​

Contact information

For more information contact:

Bill Leitch
Senior Advisor

Leah Malcolm
Project Manager

Media Inquiries Office
250-356-8241