The project scope included:
	- Traffic control
 
	- Environmental monitoring
 
	- Archaeological and cultural monitoring with participation by Matsqui First Nation
 
	- Excavation of the existing road structure
 
	- Removal and relocation of the existing light weight fill (EPS)
 
	- Ground improvements using Cutter soil-cement mixing to consolidate the soft soils
 
	- Placement of the permanent road structure
 
	- Asphalt resurfacing
 
Location
	- Highway 11 between Valley Road and Bateman Road
 
Status
	- First response efforts started in December of 2021
 
	- Analysis and design completed for each phase of construction
 
	- Initial recovery work to open Northbound lane took place January to March 2022
 
	- Southbound repairs took place from August to November 2022
 
	- Northbound permanent repairs began in June 2024 and completed in January 2025
 
Schedule
Work began in June 2024 and completed in January 2025.