To prepare for major construction, advance works and environmental rehabilitation are underway or completed at various locations along Highway 1 throughout the Program area.
Fishtrap Creek Median Preload
Preloading of compressible soils in the median of Highway 1 (approximately 1.2 km east of Mt. Lehman Road to west of Peardonville Road) to increase their weight bearing capacity and to reduce settlement.
Status
The Fishtrap Creek Median Preload Project was completed in 2025.
Cost
The contract value for the Fishtrap Creek Median Preload Project was $14.3 M.
The contract was awarded to Timbro Contracting.
Fishtrap Creek Environmental Rehabilitation
Project highlights
Temporary extension of the culverts in Fishtrap Creek as part of environmental habitat to prepare for construction.
Status
The Fishtrap Creek Environmental Rehabilitation Project was completed in 2024.
Cost
The contract value for the Fishtrap Creek Environmental Rehabilitation Project was $0.95 million.
The contract was awarded to Seyem Kwantlen Construction Ltd.
Median Soil Removal (Phase 3A)
Project highlights
Removing soil in the median of Highway 1, from approximately 950 metres west of the 264th Street underpass to approximately 1.1 km west of the Mt. Lehman Road bridge, to prepare for construction.
Status
The Median Soil Removal (Phase 3A) Project was completed in 2024.
Cost
The contract value for Median Soil Removal (Phase 3A) was $14.7 million.
The contract was awarded to Jakes Construction.
Median Soil Removal (Phase 3B)
Project highlights
Status
The Median Soil Removal (Phase 3B) Project was completed in 2024.
Cost
The contract value for Median Soil Removal (Phase 3B) was $5.5 million.
The contract was awarded to Wide Roads.
King Road Realignment
Project highlights
King Road south at Riverside Road is being realigned to accommodate the widening of Highway 1 to the south.
Improvements to this section of King Road include:
Status
Construction began on the King Road Realignment in summer 2024. It is anticipated to be completed by the end of 2025.
Cost
The contract value for the King Road Realignment Project is $5 million.
The contract was awarded to Regehr Contracting.
East Lonzo Creek Environmental Rehabilitation
Project highlights
The realignment of Lonzo Creek is designed to be set back from the limits of the new Highway 11 Interchange and will also include the following:
Status
The East Lonzo Creek Rehabilitation Project was completed in 2025.
Cost
The contract value for the Lonzo Creek Environmental Rehabilitation Project was $16 million.
The contract was awarded to Wochmel Milestone JV.
Highway 11 Advanced Works
Project highlights
Status
The Highway 11 Advanced Works Project was completed in 2025.
Cost
The contract value for the Highway 11 Advanced Works Project was $8.3 million.
The contract was awarded to Jakes Construction.

Friendly url for this page:
gov.bc.ca/fraservalleysupportingprojects
News Room
Find news about Highway 1 - 216th to 264th Widening Project
Enter your email address to subscribe to updates of this page.