Project No. 26768-0000

Last updated on April 29, 2026

Hwy 97 Woodpecker to Stoner & Quesnel Side Roads Asphalt Resurfacing (30.7 Lane Km)


Submission for Tenders Expires: May 13, 2026

Project Number: 26768-0000

Contract ID:26768MJ0000

Location: Located on Hwy 97 LKI Segment 1151 Ewing Rd to Stoner, Durrel Rd and Dale Lake Rd (Quesnel) - Cariboo District, Southern Interior Region.

Description: Full width, conventional paving (approx 19,000 tonne382659s). Scope of work includes: Mobilization, Quality Management, Signing, Traffic Management and Control, Aggregate Production, Asphalt Mix Design, Cold Milling, Asphalt Pavement, Pavement Drainage, Re & Re Barrier, Supply and Install New Barrier, Pavement Drainage, Shouldering, Temporary Pavement Marking, Joint Sealing, Site Cleanup.

 

Document
Number

Document Description

1

Cale Creek South Pit Report (2011)