Jumping Creek to MacDonald Snowshed

Last updated on March 30, 2026

Jumping Creek to Jack MacDonald Snowshed

The project involves the design and construction of improvements to 2.6 km of the Trans-Canada Highway 1 approximately 40 kilometres east of Revelstoke, including rockfall and avalanche mitigation, climate change resiliency and median divider and roadside barrier. 

Location

The project is adjacent to the recently completed Illecillewaet and extends to the western end of the MacDonald Snowshed.

Notice of work

Notification of project-related fieldwork or construction is posted on this page in advance. For the latest information on road conditions, please visit DriveBC.

To receive a notification when this page is updated, please subscribe using the form at the bottom of this page.


March 29 to April 18, 2026

Please see the three week look ahead below for the planned construction and traffic schedule. 

All closures are dependent on weather between Revelstoke and Golden. If the full closure does not occur, expect short duration stoppages to facilitate equipment crossings.

Legend
Open Open, no scheduled delays
SLAT Closures up to 30 minutes or SLAT (single-lane-alternating traffic) all traffic permitted
Full closure Two hour delay, no traffic permitted
March 29 - April 4, 2026
  Sun
Mar 29
Mon
Mar 30
Tues
Mar 31
Wed
Apr 1
Thur
Apr 2
Fri
Apr 3
Sat
Apr 4
midnight
to 1 am
Open Open Open Open Open Open Open
1 am to
3 am
Open Open Open Open Open Open Open
3 am to
6 am
Open Open Open Open Open Open Open
6 am to
8 am
Closed Closed Closed Closed Closed Open Open
8 am to
noon
SLAT SLAT SLAT SLAT SLAT Open Open
noon to
6pm
SLAT SLAT SLAT SLAT Open Open Open
6pm to
midnight
Open Open Open Open Open Open Open
April 5 - April 11, 2026
  Sun
Apr 5
Mon
Apr 6
Tues
Apr 7
Wed
Apr 8
Thur
Apr 9
Fri
Apr 10
Sat
Apr 11
midnight
to 1 am
Open Open Open SLAT SLAT SLAT SLAT
1 am to
3 am
Open Open Open SLAT SLAT SLAT SLAT
3 am to
6 am
Open Open Open SLAT SLAT SLAT SLAT
6 am to
8 am
Open Open Open Closed Closed Closed Closed
8 am to
noon
Open Open Open SLAT SLAT SLAT SLAT
noon to
midnight
Open Open SLAT SLAT SLAT SLAT SLAT
April 12 - April 18, 2026
  Sun
Apr 12
Mon
Apr 13
Tues
Apr 14
Wed
Apr 15
Thur
Apr 16
Fri
Apr 17
Sat
Apr 18
midnight
to 1 am
SLAT SLAT SLAT SLAT SLAT SLAT SLAT
1 am to
3 am
Closed SLAT SLAT SLAT SLAT SLAT SLAT
3 am to
6 am
SLAT SLAT SLAT SLAT SLAT SLAT SLAT
6 am to
8 am
SLAT Closed Closed Closed Closed Closed Closed
8 am to
midnight
SLAT SLAT SLAT SLAT SLAT SLAT  

Status

  • In design/construction

Project benefits

  • A safe passing opportunity to break up congestion queues
  • A divider to limit cross-over collisions
  • Roadside barrier to reduce severity of off road right collisions
  • Modern 100 km/hr highway geometrics
  • Avalanche and geohazard risk mitigation
  • Increased shoulder width for active transportation
  • Reduced greenhouse gas emissions from re-routing

Project design

Project map

Jumping Creek to Jack MacDonald Snowshed Project Map

Photo gallery

Know before you go

Get construction updates, traffic, weather and road conditions and plan your route.

News release

Contact information

Friendly url for this page:
gov.bc.ca/jumpingcreek

For more information about this project, contact:

Kathryn Lawrence
Project Director