The Trans Canada Highway 1 Ford Road to Tappen Valley Road Four-Laning project will upgrade approximately 4.3 km of the Trans-Canada Highway (TCH) and replace the Tappen Overhead bridge. The western limit of the project begins at Ford Road and extends through to its terminus 400 metres east of Tappen Valley Road.
Traffic impacts
Tappen Creek Detour and White Creek Detour in effect at 60 km/hr
See below for list of scheduled work that may affect traffic
No work scheduled December 20, 2024 to January 6, 2025
For the latest information on road conditions, please visit DriveBC.
Daily stoppages
Daily intermittent minor stoppages for construction equipment and trucks from Kault Hill to Ford Road
Localized reduced speed zones between Kault Hill and Ford Road to 60 km/hr during active construction and 80 km/hr during inactive times
Mondays to Saturdays
From 7:00 pm until 6:00 am - up to 30 min stoppages through the site
From 1:00 pm to 7:00 pm - up to one 20 min stoppage around 1:00 pm and one 30 min stoppage around 7:00 pm
Closures
Kault Hill eastbound rest area/brake check is closed to public/trucks
Tappen Valley Road closed from Highway 1 to 399 Tappen Valley Road until December 2025
Detour available via Bolton Road
South exit of James Road onto Sunnybrae-Canoe Point Road.
Access and Exit from James Road to be via north intersection at the Trans Canada Highway 1
Project overview
Project improvements include:
4.3 km section of the Trans-Canada Highway widened from two to four lanes
New east bound commercial carrier pullout
New frontage road system to provide safer access to the highway
Modified protected T-intersection at Tappen Valley Road
Replacement of the existing Tappen Overhead bridge
Installation of median barrier
Status
On site Contractor: Emil Anderson Construction (EAC)
Drilling and blasting at Kault Hill
Future frontage roads under construction along Kirkpatrick Road, James Road, Sunnybrae Road and Arnouse Road
Traffic flip to new Tappen Overhead Eastbound Bridge (Nov 2024)
Remove existing Tappen Overhead Bridge (Staring Nov 2024)
Westbound Tappen Creek Bridge (Starting January, 2025)
Blasting and Rock Stabilization at Kault Hill (Estimated completion March, 2025)
Skwlax Resource Management Ltd. completed advanced clearing and fencing
Schedule
Construction began: October 4, 2023
The project is scheduled to be completed by: October 31, 2026
Project benefits
Improve safety, capacity and movement of goods and services
Provide safer access to local roads for residents, commercial vehicles, tourists and travellers
Reduce travel times during peak travel periods
Wider shoulders and new frontage road system to support cyclists, pedestrians, and people using other modes of active transportation
Project cost
The total project cost is estimated at $243 million. This includes up to $82.1 million from the Government of Canada under the Provincial-Territorial Infrastructure Component of the New Building Canada Fund.