Heavy rains caused debris blockages and washed out culverts at Kenyon Creek, located just east of Sargeant Bay Provincial Park, running about 2.4 km from north to south on the Sunshine Coast of British Columbia.
The creek is adjacent to Highway 101 along its north half, and crosses Redrooffs Road at approximately 55 m elevation. The project will:
Replace washed out culvert
Repair shoulder erosion
Conditions
Redrooffs Road
One travel lane in each direction and is approximately 6.5 m wide at the Kenyon Creek crossing
The road embankment at the culvert outlet slopes down at approximately 1:1 (H:V) to the bottom of the channel
Kenyon Creek
Flows across Redrooffs Road from north to south before eventually reaching Sargeant Bay about 500 m downstream of the crossing
Channel has a bottom width of 4 to 6 m and a bank full width of 10 to 15 m
Short section of channel at the culvert inlet which a waterfall flows into
The upstream area of the waterfall contains naturally fallen woody debris
Status
Interim emergency works (Completed October 2022)
Removal of washed-out culverts and debris blockage
Repair of road embankment erosion
Additional investigations (Completed)
Measures were applied to ensure the site could withstand another fall coastal cycle in 2023
Temporary Repairs (Completed September 2023)
Delineation of roadway
Additional signage
Asphalt installation and riprap to the shoulders
Ongoing maintenance will continue until permanent repairs commence
Temporary culverts held up during the December 4th, 2023, flooding event. These temporary culverts are functioning well and flowing with no sign of issues.
Permanent repairs (Completed in 2024)
The 100% detailed design for permanent repairs was completed in January 2024
Advanced tree-clearing work was completed in March 2024
Public tender for the construction work was posted in May 2024
Contract awarded to MDBS Quattro Constructors Ltd. on June 25, 2024
Construction commenced August 12, 2024
Culverts installation completed in September 2024
Construction substantially completed on October 22nd, 2024
Construction completed on November 21, 2024
Project Team continues to work on Completion/Closeout Documentation