Kenyon Creek Culvert Replacement at Redrooffs

Last updated on December 9, 2024

Put alternative text to describe image in info box

Heavy rains caused debris blockages and washed out culverts at Kenyon Creek, located just east of Sargeant Bay Provincial Park, running about 2.4 km from north to south on the Sunshine Coast of British Columbia.

The creek is adjacent to Highway 101 along its north half, and crosses Redrooffs Road at approximately 55 m elevation. The project will:

  • Replace washed out culvert
  • Repair shoulder erosion

Conditions

Redrooffs Road

  • One travel lane in each direction and is approximately 6.5 m wide at the Kenyon Creek crossing
  • The road embankment at the culvert outlet slopes down at approximately 1:1 (H:V) to the bottom of the channel

Kenyon Creek

  • Flows across Redrooffs Road from north to south before eventually reaching Sargeant Bay about 500 m downstream of the crossing
  • Channel has a bottom width of 4 to 6 m and a bank full width of 10 to 15 m
  • Short section of channel at the culvert inlet which a waterfall flows into
  • The upstream area of the waterfall contains naturally fallen woody debris

Status

  • Interim emergency works (Completed October 2022)
    • Removal of washed-out culverts and debris blockage
    • Repair of road embankment erosion
  • Additional investigations (Completed)
  • Measures were applied to ensure the site could withstand another fall coastal cycle in 2023
  • Temporary Repairs (Completed September 2023)
    • Delineation of roadway
    • Additional signage
    • Asphalt installation and riprap to the shoulders
    • Ongoing maintenance will continue until permanent repairs commence
  • Temporary culverts held up during the December 4th, 2023, flooding event. These temporary culverts are functioning well and flowing with no sign of issues.
  • Permanent Repairs (to be completed in 2024) 
    • The 100% detailed design for permanent repairs was completed in January 2024
    • Advanced tree-clearing work was completed in March 2024
    • Public tender for the construction work was posted in May 2024
    • Contract awarded to MDBS Quattro Constructors Ltd. on June 25, 2024
    • Construction commenced August 12, 2024
    • Culverts installation completed in September 2024
    • Construction substantially completed on October 22nd, 2024
    • Project Team continues to work on Completion/Closeout Documentation.

Photo Gallery

Connect with TranBC

Visit the TranBC blog

Contact information

Friendly Url for this Page:
gov.bc.ca/kenyon-creek-project

For information about this project contact:

Lower Mainland District Phone
1-604-527-2221