Gough Creek and Clack Creek cross Day Road at approximately 1.6 km north of Highway 101. Gough Creek crosses Day Road about 210 m west of the Clack Creek crossing. The two creeks flow south and join with Roberts Creek downstream, before eventually flowing into the Strait of Georgia. The project will:
- Replace washed out culvert
- Repair shoulder erosion
Day Road
- Seal-coated, low volume road
- The road is about 5 m wide and is raised above the adjacent ground in most areas
- Surrounded by heavily forested areas
- Services approximately six rural residential lots in the Roberts Creek community
Gough Creek
- Channel is well-defined, with a typical width of 3-6 m upstream of the crossing, widening to a maximum of 12 m near the culvert inlet
- 6-10 m wide near the outlet and widens downstream to an approximately 40 m wide flood plain with a poorly defined 5 m wide channel
Clack Creek
- Channel is about 3-5 m wide upstream and widens to a maximum 20 m width near the culvert inlet
- On the downstream side, the channel is 3-6 m wide, with a floodplain that is approximately 50 m wide
Status
- Emergency Interim Repairs (Completed January 2023)
- Removal of washed-out culverts and debris blockage
- Repair of road embankment erosion
- Additional investigations (Completed)
- Measures to ensure the site can withstand another fall coastal cycle in 2023
- Ongoing maintenance will continue until permanent repairs commence
- Temporary Repairs (completed in September 2023)
- Delineation of roadway
- Riprap and gravel restructure of the shoulders
- Removal of sections of washout culverts in Clack Creek was not completed during Phase 1 and this will be completed during Phase 2 – Permanent repair works
- Temporary culverts held up during the December 4th, 2023, flooding event. These temporary culverts are functioning well and flowing with no sign of issues.
- Permanent Repairs
- The 100% detailed design for permanent repairs was completed in January 2024
- Advanced tree clearing work was completed in February 2024
- Public tender for the construction work was posted in April 2024
- Contract awarded to Heavy Civil Infrastructure Ltd. on June 27, 2024
- Construction commenced on July 29, 2024
- The project has replaced the washed-out culverts with larger concrete box culverts to accommodate future storm events and climate change
- Repairs will also address shoulder erosion and embankment strengthening
- With the rainy season approaching, interim stabilization works will be completed through to mid-December to secure these sites over winter, including placement of riprap to prevent erosion of the channel banks and roadway embankment
- Potholes will be filled, driveways repaired and road graded
- These sites will be completed in 2025, when the next appropriate environmental window for work is available
Photo Gallery