Highway widening will address narrow sections along the corridor. These improvements will increase safety and improve winter maintenance by providing a wider driving surface.
Three priority locations have been selected for highway widening, at Bell 1 North, Iskut North and Tatogga South.
Projects will be completed between 2026 and 2030. Schedules will be updated as projects advance
The total program cost is estimated at $195 million. This includes a $120 million investment from the Province and up to $75 million from Natural Resources Canada under the First and Last Mile Fund (formerly the Critical Minerals Infrastructure Fund).