If you’re unable to access this application, check current outage notices or reach out for support.
There are no limitations on who may apply; however, landowner consent must be provided for any lands where work is being done for this authorization.
All diking projects require that the local diking authority that oversees the dike has been contacted and the diking authority has agreed to the proposed works.
Under the Dike Maintenance Act (DMA), "dike" means:
Under the DMA, "diking authority” means:
A private dike is a dike built on private property that protects only that property. Private dikes are not regulated under the DMA and approvals are not required for works related to private dikes. However, work related to private dikes may require authorizations and approvals under other pieces of legislation such as the Water Sustainability Act and the Fisheries Act.
A DMA approval is a written authorization to make changes to a dike or construction of a new dike.
Before completing an application, you will need to contact your local diking authority. A list of dikes by owner/authority (PDF, 2.7MB) can be found on the Flood protection structures in B.C. site.
If the work required is to be done in or adjacent to a stream channel, then a Water Sustainability Act (WSA) change approval or notification of instream works may also be required.
There is no fee to submit DMA approval.
Review and collect the information and documents required before you start an application.
If you’re unable to access this application, check current outage notices or reach out for support.
The DMA Approval application allows the submission of multiple locations along a dike structure when appropriate. It is preferable that the application is submitted as a single site application; however, each situation is different, so we recommend contacting your regional deputy inspector of dikes to discuss your project in advance.
When preparing a multi-site application, please consider the following:
A BCeID allows you to save, reopen and check the status of your natural resource application:
Once you have assembled the required documents for your application, apply online.
If you’re unable to access this application, check current outage notices or reach out for support.
After you have submitted an application, you can amend or cancel it:
Your application will go through the following process before any decision is made about whether the change approval will be granted:
Receiving the application
When natural resource applications are submitted, it is expected that they meet the posted application requirements for that application type, both in quality and completeness, so that the proposal is ready to move towards a decision in a timely manner. The application requirements can be found under the applicable water application authorization guidance.
Poor quality or incomplete applications can result in substantial delays and create significant workload impacts to ministry staff. In order to improve application turnaround times, applicants are required to provide missing information or respond to FrontCounter BC staff requests within 2 weeks.
If applicants are not able to meet the requested timeframe, they should inform the requesting staff member as early as possible. Applications not meeting application requirements within the requested timeframes may be rejected.
If the application is returned or not accepted, applicants can expect a detailed explanation of application deficiencies. If an application is rejected due to deficiencies, applicants may re apply at their convenience.
Consultation and referrals
Applications for DMA approvals may be referred to other provincial and federal regulatory agencies for comment during the adjudication process. Consultation with First Nations, other water users, community groups or other parties may be required if existing rights could be affected by your application.
Review
Once FrontCounter BC has received all comments and objections from potentially affected parties, and any additional information provided by you or affected parties, applications undergo a technical review. During the technical review process, you may be asked to provide additional information or may be required to undertake further study to support your application. On the basis of this review, a recommendation is made for the consideration of a statutory decision maker, normally a deputy inspector of dikes, who is authorized under legislation to grant a DMA approval .
Decision
A deputy inspector of dikes will decide whether to approve your application after weighing the information and will inform you of the decision.
Read more about application processing and how to check the status of your application.
Find the FrontCounter BC office closest to you.