Traffic impacts
For the latest information on road conditions, please visit DriveBC. Drivers are reminded to drive for the conditions, observe construction-zone speed limits and follow the direction of traffic-control signs and personnel.
October - November 2025
Expect delays and plan ahead.
Alders Avenue will remain unpaved until heavy civil work is complete as ongoing works could damage new paving.
- October 27-30 - Paving on Fulford-Ganges at Seaview Rd and Cranberry Rd Intersections.
- November 1 -2 - Weekend work planned
Standard delays
Plan for delays along this route throughout the project:
- Active working hours have been increased to 7am to 5pm, Monday to Friday, with occasional work on Sundays, to allow for acceleration of the schedule and completion by summer 2025
- People travelling along the Fulford-Ganges Road should anticipate up to a 20-minute delay through the project site and are encouraged to plan ahead and avoid peak travel times to minimize delays.
- Single Lane Alternating Traffic (SLAT) is only permitted in active construction zone areas where the contractor is actively working.
- Posted speed will be reduced to 30km/h from 50 km/h during construction where the contractor is actively working
- Road closures are not permitted within 20 minutes of a ferry arrival at Fulford Harbour
- The contractor will comply with all the applicable bylaws of the Capital Regional District regarding hours of work
The project includes:
- Resurfacing and grading to provide paved shoulders on both sides of Fulford-Ganges Road
- Pulverizing the existing roadway and re-building the road base to 2-lanes including shoulders
- Constructing an underground storm sewer drainage system for almost the entire length of the project
- Placement of new pavement
- Adding additional enhancements for safety and active transportation, such as new signage, paint markings, cross walks, and refuge areas for cyclists
- Developing a staging area to install a large culvert at the creek near Cranberry Road
Schedule
- Paving along Fulford-Ganges Road is anticipated to be complete by the first week of November - weather dependant
- Overall project completion, including sideroads, intersections, driveways and Alders Ave drainage works, is expected by the end of November 2025
Project cost
$22.9 million
Project benefits
- Improved safety and sight lines for accesses, pedestrians, and cyclists
- The new pavement markings, cross walks and installation of a speed reader board would enhance visibility and safety
- Improved underground storm sewer drainage system
- New pavement and subbase gravels would extend the service life of roadway