Project Status: Design
City/Town: Langley
Project Scope: This project includes the seismic upgrade and 11 classroom addition at Peter Ewart Middle School. The project will add 275 student seats, creating a total of 900 safer seats at the school. There will be minimal impact on student learning during construction as the expansion will make use of repurposing underutilized space.
Estimated Project Value: $38.8 million
News Release: Students at Peter Ewart Middle school to get safer, expanded school
Estimated Project Milestones
Tender and Award: Spring 2023
Construction Initiation: Summer 2023
Occupancy: Fall 2024
Project Updates
School District Project Contact
Project Manager: Tristan Schaufler
Contact Number: 604-534-3294
E-mail: tschaufler@sd35.bc.ca