School District 39 - General Wolfe Elementary

Last updated on December 7, 2022

general wolfe

Project Status: Occupied

City/Town: Vancouver

Project Scope: This project includes a seismic upgrade of General Wolfe Elementary. The school was built between 1910 and 1912 in the Riley Park-Little Mountain neighbourhood and is rated as a high seismic risk. During construction, students are scheduled to attend the South Hill Education Centre swing space. Construction is expected to begin in spring 2020 and be ready for students in fall 2021. The heritage structures of the facility will remain intact.

Estimated Project Value: $20.2M

School Website

Project Website

Estimated Project Milestones

  • Tender and Award: Spring 2020
    Construction Initiation: Spring 2020
    Occupancy: Fall 2021

News Release:

School District Project Contact

Ron McDonald, Facilities Director

Phone:  604-713-5288