Project Status: Occupied
City/Town: Victoria
Project Scope: This project includes the construction and installation of a temporary 12-unit modular school with a modular gym on the property of Braefoot Elementary to be ready for students by September 2021. Space will be also available for the existing Les Rigolos before- and after-school child care program at the school in September 2021.
Estimated Project Value: $11.26 million
News Release:
Tender and Award: Completed
Construction Initiation: Spring 2021
Occupancy: September 2021
Temporary Modular Gym: Fall 2022