Project No. 12947-0001

Last updated on August 29, 2023

Highway 1 – 264 Street to Mt Lehman Road Advanced Works Median Soil Removal and Preload


Submission for Tenders Expires: September 12, 2023

Project Number: 12947-0001

Contract ID: 12947MJ0001

Location: Median of Hwy 1 approximately 950 m west of the 264th St. overpass and ending approximately 1.1 km west of Mt Lehman  Rd overpass. EB LKI Segment 0518 km 18.89 to Segment 0520 km 7.80, and WB LKI  Segment 0521 km 10.29 to Segment 0519 km 0.95.

Description: Works includes removal of soil berms at Hwy 1 median including two test fills and preloading of ditches.   This includes but not limited to: Mobilization, Quality and Traffic Management, Protection of the Environment, Clearing and Grubbing, Type D Excavation, Construction of access roads, Placement of Preload and Test Fills, Installation of Geotechnical Instrumentation, Median Grading, Revegetation seeding, and supply and install of culverts, riprap, interlocking concrete blocks, and barrier flare.

 

Document
Number

Document Description

1

Cross Sections - Rev A

2

Bradner Road Utility Preload Recommendations

3

272nd Street and Ross Road Utility Corridor Preload Recommendations

4

264th Interchange Test Fills Recommendations

5

Advance Works Bore Hole/Test Pit Logs

6

Step B Soil Characterization Program, Phase 1 Advance Works (Bradner Rest Area and Median Soils) Highway 1 – 264th Street (Langley) to Whatcom Road (Abbotsford), BC

7

2300 Tender Data – FVH1 Segment 1 Part 1 of 2

8

2300 Tender Data – FVH1 Segment 1 Part 2 of 2

9

2300 Tender Data – FVH1 Segment 2

10

Strong Pit Agricultural Reclamation Plan