Project No. 08600-0001

Last updated on May 8, 2024

Highway No. 99 Blundell Road to Steveston Interchange Surcharge Project


Submission for Tenders Expires: May 16, 2024

Project Number: 08600-0001

Contract ID: 08600MJ0001

Location: Highway 99 southbound from Blundell Road to Steveston Interchange.

Description: Implementation of 2 m min. high surcharge with 1.5H:1V slopes in the Highway 99 southbound shoulder area from Blundell Road to Steveston 1C (approximately 2.15 km).  Scope of work includes, but is not limited to:  mobilization, quality control, traffic management, construction of temporary interlocking concrete block retaining walls to avoid impacts to existing highway ditches, installation of drainage features to facilitate drainage during surcharging period, site restoration, clean up, and demobilization.

 

Document
Number

Document Description

1

Highway 99 - Blundell Road to Steveston Interchange Surcharge - Cross Sections

2

Highway No 99 - Blundell Road to Steveston Interchange Surcharge - Drainage Assessment

3

Fraser River Tunnel Project – Hwy 99 Additional Southbound Lane Geotechnical Report

4

George Massey Tunnel Replacement Project – Contaminated Sites Study (April 2015)

5

FRTP Advanced Works – COR Richmond Additional SB Lane Phase 1 Geotechnical Impact Assessment of BCH Infrastructure

6

Highway 99 – BC Hydro Distribution Infrastructure

7

Highway 99 – BC Hydro Transmission Infrastructure

8

Highway 99 Corridor Improvement Projects - Construction Environmental Management Plan

9

George Massey Tunnel Replacement Project - Corridor Improvements Projects Archaeological Chance Find Management Plan

10

Hazard Assessment Document

11

TenderData.zip