Project No. 12873-2021 Schedule T3 - Specific Reference Documents

Hot-In-Place Asphalt Road Resurfacing Highways Fraser Valley Area H3:  Hope Slide And Manning Park (103.3 Lane Km)


Submission for Tenders Expires: April 21, 2021

Project Number: 12873-2021

Contract ID: 12873MJ2021

Location: Highway 3 - Hope Slide and Manning Park

Description: The Site has two (2) locations along Hwy 3: Location A (Hope Slide) starts at LKI 0.00 and terminates at LKI 10.14. Location B (Manning Park) starts at 51.90 and terminates at 68.32. The general nature of the work includes 103.3km of HIPR with the work including, but not limited to, aggregate production, asphalt medium mix, asphalt cement with antistrip, HIPR rejuvenating agent, HIPR, joint seals, recessed roadway reflectors, pavement markings and associated works.

 

Document
Number

Document Description

1

Reclamation and Environmental Protection Handbook for Sand, Gravel and Quarry Operations in British Columbia 

2

Health, Safety and Reclamation Code for Mines in British Columbia

3

Aggregate Operators Best Management Practices Handbook for British Columbia –  Volume 1 

4

Aggregate Operators Best Management Practices Handbook for British Columbia – Volume 2

5

Health & Safety - A Practical Guide for Aggregate Operations

 

Pit Information

6

11 Mile Pit #1713 – Pit Development Plan - 22X34

7

11 Mile Pit #1713 – Pit Development Plan - 22X34 - ORTHO

8

11 Mile Pit #1713 – Pit Development Plan – 11x17 - ORTHO

9

Test Pit/Hole Summary Sheets - ATHS1713-1994-2021

10

Eleven Mile Sieve Analysis Reports

11

Source Detail Report - Eleven Mile (1713)

12

11 Mile Pit Photos

13

Eleven Mile Pit Site Plan