School District 39 - Sir Charles Kingsford-Smith Elementary

Project Status:  Occupied

City/Town:  Vancouver

Project Scope: This project includes seismically upgrading 18 classrooms, the library, and the gym with reinforced walls and columns. The project also includes installing an accessible elevator and washrooms for people with disabilities, as well as new storm and water lines. These upgrades will ensure the building is structurally safe from earthquakes and provide students and staff with a more modern and efficient space for years to come.

Estimated Project Value:  $ 11.6M

School Website

Project Website

Estimated Project Milestones

  • Tender and Award: Summer 2017
  • Construction Initiation: Summer 2017
  • Occupancy: Fall 2018