School District 33 - Promontory Heights Elementary Community School
Project Status: Occupied
City/Town: Chilliwack
Project Scope: This project includes a two-storey addition to be built on the west side of the school, creating 200 new student spaces to support the school’s rapidly growing enrolment. This project will move students from the school’s eight existing portables into the new classrooms. It will feature a new multi-purpose area and open and collaborative learning spaces to support B.C.’s new curriculum. The new addition will be built to Leadership in Energy and Environmental Design (LEED) Gold standard.
Estimated Project Value: $6.1M
Estimated Project Milestones:
Tender and Award: Summer 2017
Construction Initiation: Summer 2017
Occupancy: Spring 2018
Project Updates:
School District Project Contact
Gerry Slykhuis, Secretary Treasurer
Contact Number: (604) 703-1781